Within the framework of the powers granted to the Ministry of Mines and Energy (“MME”) by means of Article 2.2.2.28. of Decree 1073 of 2015 and after the UPME delivered in July of this year the “Technical Study for the Natural Gas Supply Plan 2019-2028”, the MME adopted the Natural Gas Supply Plan 2019-2028 by means of Resolution 40304 of October 15, 2020. This supply plan presents the description of the most important projects to supply the demand for gas in the country, among which is the natural gas import infrastructure to be developed in the Pacific ocean, which includes the regasification plant and the Buenaventura – Yumbo gas pipeline.

One of the UPME´s recommendations regarding the gas import infrastructure in the Pacific Ocean, is that it should reach its operation date by 2024, considering that according to calculations it is highly probable that an El Niño phenomenon occurs in 2024, leading to high gas consumption in the country. Therefore, and in order to meet the increased demand, it was decided that certain incentives should be adopted for the early completion of the project, and therefore it is useful to establish regulatory conditions to reward the early completion. CREG will be in charge of adopting such invectives through its regulatory faculties, not only for the aforementioned project but for all projects included in the plan in accordance with Article 2 of the plan.

As a result, the following projects were included in the Natural Gas Supply Plan:

 

Project

Description

COD

Transport capacity in the Mariquita – Gualanday section.

Design, adaptation and construction of the necessary infrastructure to guarantee a transport capacity of 20 million cubic feet per day (“MCFD).

December 2020

Bidirectional Barrancabermeja – Ballena

Design, adaptation and construction of the necessary infrastructure to guarantee a bidirectional transport capacity of 100 MCFD.

December 2020

Bidirectional Barranquilla – Ballena

Design, adaptation and construction of the necessary infrastructure to guarantee a bidirectional transport capacity of 170 MCFD.

December 2020

Interconnection Barranquilla – Ballena with Ballena – Barrancabermeja

Design, adaptation and construction of the necessary infrastructure to guarantee the interconnection of the Barranquilla – Ballena section and the Ballena- Barrancabermeja section with a capacity of bidirectional transport of 170 MCFD.

December 2020

Expansion of the Jamundí – Valle del Cauca Branch Transport Capacity

Design, adaptation and construction of the necessary infrastructure in the Jamundí branch that guarantees the attention of the demand in the Popayán node of 3 MCFD.

December 2020

Bidirectional Yumbo – Mariquita

Design, adaptation and construction of the necessary infrastructure to guarantee a bidirectional transport capacity of 250 MCFD.

58 as of the date of the selection of an investor for the execution of the natural gas import infrastructure. No later than December 2024.

Pacific Regasification Plant located in the Buenaventura Bay – Valle del Cauca

·        Regasification capacity of no less than 400 MCFD.

 

·        Storage capacity of no less than 170,000 m3 of liquefied natural gas – LNG

58 months as of the date of the selection of an investor for the execution of the project. No later than December 2024.

Gas pipeline from the Regasification Plant located in the Buenaventura Bay to a delivery point to the National Transportation System in Yumbo

Transportation capacity of no less than 400 MCFD at a delivery point in the National Transportation System in Yumbo

58 months as of the date of the selection of an investor for the execution of the project. No later than December 2024.

 

The UPME will be in charge of the investor selection processes as mentioned in article 3 of the plan.